A design fee is payable for projects involving:
Once you have received the formal quote and you want to proceed, simply sign the Quote Acceptance form and return it to us.
We will issue an invoice for the work which will need to be paid before any scheduling or construction can begin.
Please note: commencement of your works may take up to 12 weeks following the payment of your construction invoice.
You can request a customer reference number (CRN) by phoning 1800 267 926 or you can complete request to install a new temporary or permanent meter using the form below.
Please note:
Once the power supply is available at your property, your electrician or builder may need to carry out further work.
When your electrical contractor has completed their work, your contractor needs to submit the necessary electrical notices to us for approval (preliminary and completion notices). When these have been approved, your electricity will be connected (meter installed) and you will begin being invoiced for your power supply.
A design fee is payable for projects involving:
Once you have received the formal quote and you want to proceed, simply sign the Quote Acceptance form and return it to us.
We will issue an invoice for the work which will need to be paid before any scheduling or construction can begin.
Please note: it can take up to 12 weeks for work to be completed from receipt of payment.
You can request a customer reference number (CRN) by phoning 1800 267 926 or you can request to install a new temporary or permanent meter using the form below.
Please note:
Once the power supply is available at your property, your electrician or builder may need to carry out further work.
When your electrical contractor has completed their work, your contractor needs to submit the necessary electrical notices to us for approval (preliminary and completion notices). When these have been approved, your electricity will be connected (meter installed) and you will begin being invoiced for your power supply.
You can request a customer reference number (CRN) by phoning 1800 267 926 or you can request to install a new temporary or permanent meter using the form below.
Please note:
When your electrical contractor has completed their work, your contractor needs to submit the necessary electrical notices to us for approval (preliminary and completion notices). When these have been approved, your electricity will be connected (meter installed) and you will begin being invoiced for your power supply.
You can request to install a new temporary or permanent meter using the form below.
You can request to relocate one of our assets using the form below.